格式版本: 2
标题: "DOE Keeps Eddystone Plant Online Amid Data Center Demand Surge"
原文链接: "https://www.datacenterknowledge.com/energy-power-supply/doe-extends-eddystone-as-pjm-faces-data-center-power-surge"
发布日期: "2026-08-26"
发布时间校准状态: "found"
发布时间需复核: "否"
发布时间来源: "rule:configured_publication_date_rule"
发布时间证据: "datacenterknowledge-jsonld-date-published html:original: \"datePublished\":\"2026-08-25T19:54:43.000Z\""
发布时间校准原因: "信源发布日期识别规则直接确认发布时间"
发布时间校准置信度: "high"
发布时间候选数量: 2
发布时间严格候选数量: 2
发布时间原页读取状态: "source template page reused from URL open"
发布时间未找到原因: ""
发布时间校准时间: "2026-08-26T20:52:45+08:00"
发布时间仲裁状态: "skipped"
发布时间仲裁尝试次数: 0
发布时间仲裁耗时毫秒: 0
发现时间: "2026-08-26T20:52:12+08:00"
入库时间: "2026-08-26T12:52:46.068Z"
来源平台: "Data Center Knowledge 搜索"
搜索渠道: "source_template"
搜索词: "https://www.datacenterknowledge.com/search?q=AI%20Rack"
匹配关键词:
  - "AI Rack"
  - "AI"
相关厂家:
  []
相关专家:
  []
内容类型: "网页"
抓取工具: "Free Fetch + Defuddle"
清洗工具: "Defuddle Markdown + Defuddle/Readability 正文提取"
原始附件:
  []
AI优质: "否"
AI打分: 53
AI分档: "非优质"
AI质检状态: "不通过"
AI打分理由: "正文主线是DOE延长Eddystone电厂运行以应对PJM数据中心负荷增长和发电缺口，并非超节点或机架级AI基础设施。Data Center Knowledge为专业媒体，链接DOE命令并包含PJM、Constellation及专家采访；相较固定知识库，新增了延长至11月20日、760MW保供、15GW数据中心负荷及失负荷压力测试等可核验事实。页面本身完整且可追溯，但缺少AI机架拓扑、关键部件路线、机架级供电机制或具体AI平台部署，商业动作也仅属于电网保供，未命中高价值准入通道，按弱相关基础设施报道否决。"
AI质检模型: "gpt-5.6-sol"
AI质检时间: "2026-08-26T20:53:48+08:00"
AI主题相关性: 6
AI来源权威性: 13
AI新颖性: 15
AI技术细节: 6
AI商业部署信号: 4
AI完整性: 9
AI评分提示词版本: "v17-精简生产版"
AI评分提示词SHA256: "48fb9777f386026761b4873eaff30807694fb11e9b352d7c69bf2dfde750cc7d"
AI评分知识库版本: "knowledge_base_v1-20260819+runtime.2"
AI评分知识库SHA256: "1299bb38bf43f7ee6a8aa444593284c6ef752e279cbead2087a1b6a93e2578ff"
AI评分知识库检索词: "[\"AI Rack\",\"RAS\",\"DOE\",\"MW\",\"PJM\",\"PPL\",\"GW\",\"www.energy.gov/documents/doe-order-no-202-26-40\",\"PECO\",\"CORRECTION\"]"
AI评分知识库命中: "[{\"id\":\"runtime-f624b95312e2afb0b2d8ef03\",\"title\":\"https://www.datacenterknowledge.com/data-center-construction/lancium-nvidia-partner-on-gigawatt-scale-ai-data-centers\",\"sourceType\":\"ai_excellent_article\",\"time\":\"2026-08-25\",\"matchedTerms\":[\"RAS\",\"DOE\",\"MW\",\"PPL\",\"GW\"],\"rank\":-10.953175869567772},{\"id\":\"historical-jun-042\",\"title\":\"AI Rack/机柜级超节点架构，详细列出Vera Rubin/GB200 NVL72规格、NVLink 6互连、HBM3e、液冷与供电设计，具备明确的产品化与\",\"sourceType\":\"curated_item\",\"time\":\"2026-06\",\"matchedTerms\":[\"AI Rack\"],\"rank\":-7.644040698397363},{\"id\":\"historical-jun-056\",\"title\":\"两项全新升级规范开放下载！锁定超节点与 GW 级 AIDC 技术论坛\",\"sourceType\":\"curated_item\",\"time\":\"2026-06\",\"matchedTerms\":[\"GW\"],\"rank\":-7.553671107365397},{\"id\":\"historical-may-048\",\"title\":\"52页！液冷行业深度报告：液冷市场需求驱动因素、液冷技术方案及演进路径、全球液冷介质市场规模及构成、境内外液冷厂商及市场竞争格局\",\"sourceType\":\"curated_item\",\"time\":\"2026-05\",\"matchedTerms\":[\"MW\"],\"rank\":-6.056348710583856},{\"id\":\"july-correct-0012\",\"title\":\"Microsoft to deploy AMD Helios rackscale solution to support inference workloads and Azure services\",\"sourceType\":\"labeled_article\",\"time\":\"2026-07\",\"matchedTerms\":[\"AI Rack\",\"RAS\",\"PPL\"],\"rank\":-5.420756419296833}]"
AI摘要: "美国能源部要求PJM和Constellation将宾州Eddystone电站760MW机组继续运行至11月20日，这是该电站原定2025年退役后的第六次紧急延期，以应对以数据中心为主的负荷激增与发电退役带来的供电可靠性风险。"
AI摘要模型: "ali-deepseek-v4-flash"
AI摘要时间: "2026-08-27T08:12:54.289Z"
采集批次: "2026年8月26日20点37分07秒"
采集批次ID: "20260826-203707-934"
去重键: "https://www.datacenterknowledge.com/energy-power-supply/doe-extends-eddystone-as-pjm-faces-data-center-power-surge"
---

## DOE Keeps Eddystone Power Plant Online Amid Data Center Demand Surge

The 760 MW Eddystone power plant will remain online longer as PJM faces rising data center load, generator retirements, and delayed power resources.

The Eddystone power plant in Pennsylvania will stay online longer as emergency reliability insurance while PJM awaits replacement generation.Constellation Energy

The Department of Energy (DOE) has ordered PJM Interconnection and Constellation Energy to keep 760 MW of generation at Pennsylvania’s Eddystone Generating Station available to operate through Nov. 20, extending an emergency measure as the grid faces rising electricity demand and a wave of generator retirements.

The DOE’s reliability analysis includes roughly 25 GW of projected PJM load growth, including 15 GW from data centers, against about 17 GW of announced fossil-fuel retirements.

The [Aug. 21 order](https://www.energy.gov/documents/doe-order-no-202-26-40), issued under Section 202(c) of the Federal Power Act, requires PJM to economically dispatch Eddystone Units 3 and 4 when needed. It also says the units “shall not be considered a capacity resource.”

[The two units](https://www.constellationenergy.com/about/locations/eddystone-generating-station.html) are 380 MW each and can run on natural gas or oil. They were scheduled to retire May 31, 2025, but DOE has repeatedly directed that they remain available.

“The core problem is timing: load is arriving faster than replacement generation, and transmission can become executable,” said Neil Osnato, founder of Persistence Analytics Group.

## Data Center Growth Meets Retiring Generation

DOE’s modeling estimated around 430 loss-of-load hours in average weather, rising to 1,052 hours under worst-case conditions with maximum unserved load of approximately 21.3 GW. While these are stress scenarios rather than forecasts, they illustrate why DOE considers the combination of load growth and retirements a reliability concern.

Darryl Lawrence, Pennsylvania’s consumer advocate and head of the state’s Office of Consumer Advocate, said PJM’s reliability position has changed significantly after decades of maintaining ample reserve margins.

“During extreme weather conditions, PJM’s system is fragile,” Lawrence said. “And this is not something that we’ve seen in my time in the business, which is 20-plus years.”

The department’s order points to a “timing mismatch between resource retirements, load growth and the pace of new generation entry.” New generation and transmission can take years to develop, while data center projects can add hundreds of megawatts of demand in individual locations.

Lawrence said the recent influx of large data centers has changed the assumptions PJM has relied on for decades.

“We haven’t seen this kind of forecasted demand in the PJM system since the days when they were building steel mills,” Lawrence said.

## Multiple Extensions

The Aug. 21 order is the sixth DOE directive extending or preserving Eddystone’s availability since its scheduled 2025 retirement.

Lawrence said the repeated emergency interventions suggest PJM’s mechanisms, which worked well for decades, are struggling to keep pace with unprecedented forecasted demand not seen since the steel mill.

A PJM spokesperson told Data Center Knowledge that the grid operator supports DOE action to defer generator retirements in its footprint, citing the growing risk of a supply-demand imbalance as generation retires while demand rises.

PJM forecasts 32 GW of load growth by 2030, with 30 GW of that growth expected to come from Large Loads, primarily data centers. The grid operator also broke its all-time peak load on July 2, reaching an estimated 168,158 MW, according to preliminary data.

Elizabeth Whitney, managing principal at Meguire Whitney, said the repeated use of Section 202(c) reflects a broader shift in how the federal government approaches energy emergencies.

The authority has historically functioned as a short-term reliability tool, Whitney said. But the Trump administration’s declaration of a national energy emergency has created a broader framework for repeated use of the authority.

“If there is a statutory benefit to being in an emergency situation, then there’s going to be political pressure to find an emergency to justify that use,” Whitney told Data Center Knowledge in a phone interview.

That does not necessarily mean the orders are unjustified, she said. But repeated reliance on emergency authority raises the question of how long an emergency measure can remain in effect before it effectively becomes part of normal resource planning.

## Who Pays for the Emergency?

The DOE order requires PJM to use economic dispatch to minimize costs to ratepayers, but it does not settle the larger question of who ultimately pays to keep retiring generation available.

Whitney said those costs generally flow through the market, meaning they can ultimately affect electricity customers. She said that raises a broader question about whether large loads that drive the need for additional reliability resources should bear more of those costs.

A spokesperson for Constellation told Data Center Knowledge that it has reached an agreement with PJM to recover the costs of complying with the DOE order, including operating and required maintenance costs. PJM is allocating those costs using the same approach it uses for capacity costs, according to Constellation.

Lawrence said Pennsylvania’s large-load tariff uses a ‘but for’ test: if infrastructure wouldn’t be built without a specific customer, that customer should bear the cost.

Applying that principle to Eddystone is more difficult. Electricity cannot be traced to a specific generating unit or data center, making it difficult to establish a direct relationship between a large load and the cost of preserving a retiring plant.

PJM’s recent [large-load reforms](https://www.datacenterknowledge.com/energy-power-supply/pjm-says-ai-data-centers-must-bring-capacity-to-earn-firm-service) could change the conditions under which future data centers connect to the grid, but they do not solve the immediate problem of generation already scheduled to retire.

“Eddystone addresses the supply side of an existing timing gap,” Osnato said. “PJM’s large-load reforms address the demand-entry side of the future gap.”

The two issues are connected, but they operate on different timelines.

## How Much Data Center Load Will Arrive?

The uncertainty around future data center demand complicates the reliability picture.

The 15 GW of data-center load in DOE’s model accounts for 60% of the total 25 GW of projected PJM load growth. But that demand is less certain in timing and scale than a generating plant that has already announced its retirement.

“A generator retirement is relatively binary. A 15 GW data-center forecast is not,” Osnato said.

Lawrence raised another problem with large-load forecasting: the same data center project can appear in multiple utility forecasts while developers negotiate for service.

A developer could discuss a project with PECO and then approach PPL, for example, potentially causing both utilities to include the prospective load in their forecasts even though the project ultimately would connect to only one system.

“We potentially have a double-counting problem,” Lawrence said.

Whitney said power constraints could also change the projections as developers adjust their plans to secure electricity.

“I don’t know that we can really reliably trust any modeling right now that is even three to five years out,” Whitney said.

That uncertainty does not mean projected demand can be ignored. But it raises the question of how much confidence grid planners should place in long-term, high-load forecasts when those forecasts influence decisions about retiring existing generation.

“If forecast large-load growth is consequential enough to justify preventing physical generation from retiring, then the durability of that demand assumption becomes part of the reliability question itself,” Osnato said.

DOE’s order does not attribute the need to preserve Eddystone to data centers alone. Its analysis reflects the combined effects of load growth, generator retirements and the pace at which new resources can enter service.

Whitney said the issue ultimately extends beyond Eddystone and PJM’s immediate reliability needs. Congress has yet to establish a broader framework for the scale of the [AI infrastructure buildout](https://www.datacenterknowledge.com/energy-power-supply/pjm-5-year-strategy-wrestles-with-data-center-boom) and its demands on energy and other resources.

“The benefit side of the equation has not changed to keep pace with the tax on resources that these larger data centers are proposing,” Whitney said.

She expects pressure for data center legislation to increase as lawmakers return from August recess, but said Congress faces limited time to develop a comprehensive response before the end of the year.

For now, Eddystone remains available.

“That’s why I see 202(c) as emergency reliability insurance,” Osnato said. “It is a bridge, not a design.”

(CORRECTION: An earlier version of this story incorrectly identified Eddystone as a "coal plant." The units are powered by oil or natural gas).